Modern Underground Gold Mine Development in South Africa
Bara Consulting served as lead independent mining engineering consultant for the Qala Shallows Project, the first phase of West Wits Mining’s Witwatersrand Basin Project. The project targets approximately 70,000 oz Au annually over a 17-year mine life, with first gold achieved in March 2026. Estimated total revenue of ~US$2.7 billion. ~7.24 Moz Au mineral resource at 4.0 g/t Au.
West Wits Mining
Gold
Witwatersrand Basin
Underground Gold Mine Development
The Qala Shallows Project is the first phase of the broader Witwatersrand Basin Project developed by West Wits Mining, located within the historic Central Rand Goldfield near Johannesburg. Positioned as one of South Africa’s first new underground gold mine developments in more than 15 years, the project represents a significant milestone for the country’s mining sector and renewed investment in the Witwatersrand Basin.
Bara Consulting acted as the lead independent mining engineering consultant for the Definitive Feasibility Study (DFS), optimisation studies, and technical development of the Qala Shallows Project. Bara provided multidisciplinary mining engineering, infrastructure engineering, cost modelling, scheduling, and operational readiness support to help advance the project from feasibility through construction and production readiness.
The project focuses on relatively shallow sections of the Kimberley Reef system and leverages existing historical mining infrastructure, enabling lower upfront capital requirements and supporting a modern mechanised underground mining operation.
The updated Definitive Feasibility Study confirmed the technical and economic viability of the Qala Shallows Project as a modern mechanised underground gold mining operation in South Africa. Optimisation work completed by Bara Consulting demonstrated materially improved project economics, supporting the advancement of the project into underground development, construction, ore production, and commissioning activities.
The project achieved first gold production during 2026 and has been recognised as an important milestone for the South African mining industry, highlighting the potential for new underground gold mining projects within the Witwatersrand Basin using modern mining methods and lower capital intensity strategies.
| Item | Detail |
|---|---|
| Client | West Wits Mining |
| Project | Qala Shallows Gold Project |
| Location | Johannesburg, South Africa |
| Commodity | Gold |
| Project Type | Underground Gold Mine Development |
| Study Level | DFS / EPCM Support |
| Bara Services | Mining Engineering, Infrastructure Engineering, Costing, Financial Evaluation, Optimisation |
| Mining Method | Mechanised underground mining |
| Mineral Resource (WBP) | ~7.24 Moz Au @ 4.0 g/t Au |
| Qala Shallows LoM | ~16.8 — 17 years |
| Planned Steady-State Production | ~70,000 oz Au per annum |
| Total Gold Production | ~944,000 oz Au |
| Average Recovered Grade | ~2.60 g/t Au |
| Estimated Revenue | ~US$2.7 billion |
| AISC | ~US$1,181/oz |
| First Gold | March 2026 |
| Employment | 1,000+ direct jobs during Phase 1 |
Underground tin, tungsten and tantalum mining across Musha, Nyakabingo and Rutongo operations in Rwanda. Mine planning, design and feasibility study support across a critical minerals portfolio.
Underground mining evaluation for the Bibiani Gold Mine in Ghana’s Sefwi Gold Belt. Concept mine design, scheduling, infrastructure review and technical-economic evaluation for future underground redevelopment.
Open-pit uranium mine restart and optimisation in the Namib Desert, Namibia. Mine planning, scheduling and operational support for the successful 2024 restart of one of Namibia’s flagship uranium operations.
Copyright © 2026. All rights reserved.